METHODE PERT                                                  2/2

                                                   Application











































                        F  J  B  C  D


                        2 + 4 + 4 + 6 + 3 = 19 jours










                  T‚che                  Marge libre             Battement aval             Marge totale



                     G                         0                         4                         4


                     H                         2                         2                         4


                     A                         8                         0                         8


                     E                         0                         2                         2


                     I                         1                         1                         2


                     K                         2                         0                         2